How is fair market price determined for
an 8(a) contract?
(a) The procuring activity
determines what constitutes a fair market price for an 8(a) contract.
(1) The procuring activity must derive the estimate of a current fair market price for a
new requirement, or a requirement that does not have a satisfactory procurement history,
from a price or cost analysis. This analysis may take into account prevailing market
conditions, commercial prices for similar products or services, or data obtained from any
other agency. The analysis must also consider any cost or pricing data that is timely
submitted by SBA.
(2) The procuring activity
must base the estimate of a current fair market price for a requirement that has a
satisfactory procurement history on recent award prices adjusted to ensure comparability.
Adjustments will take into account differences in quantities, performance, times, plans,
specifications, transportation costs, packaging and packing costs, labor and material
costs, overhead costs, and any other additional costs which may be appropriate.
(b) Upon the request of SBA, a procuring activity will provide to SBA a written statement
detailing the method it has used to estimate the current fair market price for the 8(a)
requirement. This statement must be submitted within 10 working days of SBA's request. The
procuring activity must identify the information, studies, analyses, and other data it
used in making its estimate.
(c) The procuring activity's
estimate of fair market price and any supporting data may not be disclosed by SBA to any
Participant or potential contractor.
(d) The concern selected to perform an 8(a) contract may request SBA to protest the
procuring activity's estimate of current fair market price to the Secretary of the
Department or head of the agency.